Andritz awarded contract to supply pump-turbine units to China

Andritz has received an order from Shaanxi ZhenAn Pumped Storage Co. Ltd., a subsidiary of State Grid Corporation of China (SGCC), for the supply of four 350-MW reversible pump-turbines and motor-generators, together with auxiliary equipment, for the ZhenAn pumped storage hydropower plant.

Andritz has received an order from Shaanxi ZhenAn Pumped Storage Co. Ltd., a subsidiary of State Grid Corporation of China (SGCC), for the supply of four 350-MW reversible pump-turbines and motor-generators, together with auxiliary equipment, for the ZhenAn pumped storage hydropower plant.

The plant is located in Shaanxi province and will be the first pumped storage power station in northwest China. The contract value amounts to more than €100 million euros (US$114 million).

The four 350-MW units will operate with a water head of 440 m. Andritz says the first unit will be commissioned by the end of March 2023, and all units will be put into commercial operation by the end of December 2023.

After completion, Andritz says, ZhenAn will be used for peak regulation, frequency regulation, and as a synchronous condenser. In addition, it will serve as emergency standby reserve and black-start capacity for the Shaanxi power grid.